Dear Community,
i had the following question in my ACP Exam and can´t solve it by myself.
Your Scrum Software type project only uses a single shared workflow. The resolutions needs to be set manually during the Fix Transition As a project administrator, how can you achieve this ?
A. Add the Resolution field to the screen associated with Fix transition.
B Add the Resolution field to all project screws.
C Check the Set Resolution option on the target status in your board configuration.
D Request a post-function to be configured for the Fix Transition
E Request a screen with the Resolution field to be associated with the Fix Transition
I definitely need the reason for the right answer. In my opinion it only could be "D"
Because: As a project administrator i´m not able to configure transition screens !
Please give me an explanation if i´m wrong
You can not create SQL queries and put the result into dashboards without a plugin.
There are some plugins such as SQL Reporter for Jira which let's you to create sql queries.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.