Currently, the change in the value of a subtask's story point triggers the sum of the subtask's story pon the parent task's story point in an automated manner. At this time, is it possible to sum the story points of tasks other than those with a status of Done?
The Story Points custom field is not configured as Global Context or Story is not configured as Chosen Applicable Issue Types.
Find the Story Points custom fields and click on the "Cog" icon then select "Configure".
I went into the field configuration in JIRA and it is already set to Global Context.
I'm still getting the same issue the user is having where when I commit changes the points aren't coming over. I've not changed anything about the fields.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Same for me, any solution?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.