You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hi guys,
I have a project called A and i want to check how the issues that were in "In progress" on January 31st 2023.
Thanks guys
Hi @Ismail Sanni Welcome to Atlassian Community!
To get list of issues which are in "In Progress" only on 31st January :-
status was in ("In Progress") ON "2023/01/31" AND status was not in ("In Progress") BEFORE "2023/01/31" AND status was not in ("In Progress") AFTER "2023/01/31"
To get list of issues which are in "In Progress" on 31st January, it includes all issues which moved to In Progress in 2022 or before 31 st Jan :-
status was in ("In Progress") ON "2023/01/31"
Thanks,
V.Y