Hi Team,
I am using Team managed Project in my Organization. In my project Board, i am not able to see Board settings option. I am the Administrator for my Project.
I want to change "Remaining Estimate and Time Spent" in my Burn down chart where it is currently showing Original Estimate in Burn down chart(In Y axis).
Please suggest.
Hello @sreedhar murthy
For the Sprint Burndown chart in a Team Managed project Scrum board the Y axis can be either Original Estimate or Story Points. To change the selection go to Project Settings > Features. Then find the Estimation option and change the selected radio button.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Welcome to the Atlassian Community!
It's called "configure board" in Team-managed projects - that's in your screenshot, but you won't be able to change the estimates are shown here. (It wouldn't be a burn chart if it wasn't showing original estimate)