My Project Timeline does not show epics

Özge Özgenç April 30, 2024

Hello, 

I am not able to see any epics and tasks on my timeline, I believe some settings changed but could not figure out. I am adding a screenshot. Could you help me to resolve this? rws.png

1 answer

1 accepted

1 vote
Answer accepted
Mohanraj Thangamuthu
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 30, 2024

Hello, Good day. On the same board please go to backlog and provide the JQL filter query used on this board. We need to make sure JQL used on the board returs Epic issues as well.

Özge Özgenç May 2, 2024

hello @Mohanraj Thangamuthu thank you for your answer I am using this jql "project = RWS AND issuetype != Bug AND issuetype != Sub-task and issuetype = Task" 

How can I fix it?

Mohanraj Thangamuthu
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 2, 2024

Please use following JQL to include Epic

 

project = RWS AND issuetype != Bug AND issuetype != Sub-task and issuetype in (Task, Epic)

Özge Özgenç May 2, 2024

Thank you @Mohanraj Thangamuthu , that works!

Like Mohanraj Thangamuthu likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Site Admin
TAGS
AUG Leaders

Atlassian Community Events