My Child Issues Aren't Appearing In My Board or Backlog

GlenellRosburg
Contributor
February 15, 2022

I have created this child issue. But It doesn't appear in my backlog or board.

Placeholder.pngPlaceholder backlog.png

2 answers

1 accepted

2 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 15, 2022

Hello @GlenellRosburg 

Welcome to the community.

Are you working with a Team Managed project or a Company Managed project?

It looks like you might have a Type quick filter activated. Can you try clicking Clear Filters and then see if the child issue is listed?

Is the child issue you created a Sub-task type of issue? Those don't display in the Backlog view typically.

GlenellRosburg
Contributor
February 15, 2022

This a Team Managed project.

I have removed my Type filter! Thank you for that tip.

Yes, this is a child issue that I created as a subtask. Do you know the reason why the child tasks wouldn't appear in the backlog and boards? 





Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 15, 2022

It is by design that Sub-tasks do not appear in the backlog. Sub-tasks are not independent items, but rather children of their parents. The Backlog is designed to show the independent items.

In the Board view you can show the Sub-tasks by changing the grouping for the board to Subtasks.

Screen Shot 2022-02-15 at 10.14.00 AM.png

Otherwise, sub-tasks are indicated by the child task symbol on their parent issue.

Screen Shot 2022-02-15 at 10.16.35 AM.png

The same symbol appears on the parent issue in the Backlog.

Like Tasnim Ahmed likes this
Josephine Marie Neric
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 13, 2022

Hello @Trudy Claspill I was googling on how to make the child task symbol appear and chanced upon this thread. I have 2 diff. jira projects and one of them, this child task symbol is appearing automatically in the backlog but in the other one, it doesn't. Would you know how to make it appear? thanks!

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
October 13, 2022

Hello @Josephine Marie Neric 

Welcome to the community.

What type of project is being referenced by the board where the symbol doesn't appear; Company Managed or Team Managed? That will be shown at the bottom of the navigation pane on the left.

And is the project a Software, Service, or Business project?

I believe the symbol will be displayed only in boards for Team Managed Software projects, but I have not experimented with other types of Team Managed projects.

It will not be displayed for boards referencing Company Managed projects.

Madie Schneider June 28, 2023

Hello @Trudy Claspill ,

 

I have a team-managed project and our sub tasks are not showing up in our board when we filter by assignee. It is proving problematic as our workflow is to assign people sub tasks but they aren't able to filter by their assigned work to view. Any insight as to why sub tasks do not show up in the filter view? I looked into the group by: feature but I am only able to group by status, priority and assignee currently. Any insight is appreciated! 

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
June 28, 2023

Hello @Madie Schneider 

I have a suspicion that you are using a Work Management project. Does your board look something like this?

Screen Shot 2023-06-28 at 3.24.35 PM.png

If so, you are indeed using a Work Management project.

In Work Management projects on the Board view the filters are applied to the parent issues only. Subtasks are available for display only when their parent issue is displayed.

If you go to the List view and filter by assignee the results will show each item assigned to that person explicitly, even subtasks.

Madie Schneider June 29, 2023

Hi there, thanks so much for getting back to me! I will use the list view moving forward. Appreciate it!

Like Trudy Claspill likes this
0 votes
GlenellRosburg
Contributor
February 15, 2022

Thank you very much. This information really helps me figure out our processes. :)

Madie Schneider June 28, 2023

Hello,

 

I have a team-managed project and our sub tasks are not showing up in our board when we filter by assignee. It is proving problematic as our workflow is to assign people sub tasks but they aren't able to filter by their assigned work to view. Any insight as to why sub tasks do not show up in the filter view? I looked into the group by: feature but I am only able to group by status, priority and assignee currently. Any insight is appreciated! 

Suggest an answer