You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
My scrum project had 2 boards. I deleted 1 of them, and now I can't see some of the sprints from past weeks... Both boards were in my project for months already... Is there how to either recover the deleted board or to show the missing sprint tag in the roadmap?
Hello @Thiago C
Welcome to the Atlassian community!
Unfortunately there is no way to recover a deleted board.
A Sprint is created within a board, but may be displayed in multiple boards. Boards display issue based on the board filter. If there is an issue within scope of the board filter (Board A) and the issue is assigned to a sprint that was created in a different board (Board B), that other board's (Board B's) sprint will show in the first board (Board A). This is because an issue can be assigned to one and only one Active or Planned sprint at a time. So, any sprint to which an issue is assigned will show up in all scrum boards where that issue is included.
In the Free product plan you would be using the Basic Roadmap functionality (unless you are using a third party app for your roadmaps).
Based on my experimentation with the Basic Roadmap functionality, the Roadmap is associated with a single board. A given Roadmap shows only the sprints that were created in the board to which the Roadmap is associated. The board may display sprints from other boards, but the Roadmap will not show those sprints. This appears to be true based on my experiments.
If you have deleted a Board, then the Roadmap for that board also is gone. Subsequently the sprints that were created in that board have no Roadmap in which they can be displayed.
Hi Trudy, thanks for the quick revert!
I am using the basic roadmap functionality, however when both boards were active I could see all issues within the same roadmap inside either board...
Anyway, the bottom line now is whether I can re-assign past sprints to the only board I got, so the roadmap can be complete. Would you know?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There is no way in the UI that I know about to move a sprint from one board to another.