I have a task which is split into 4 subtasks. Thes have been completed and had their time spent and remaining time updated. However the parent tasks time spent is still zero and seems to require me to manually update it! Surely it should inherit the sum of the time spent on its subtasks?
Hi Lee,
You should be able to select "Include Subtasks" on the right below the estimations of the parent task. Keep in mind that you can also log work on the parent task (independent from the sub tasks)
Best regards,
Peter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ok, I have found it. However it is already ticked. So it clearly does not work.... This surely has to be simple. All I need is the parent task to auto update with its childrens time spent.... To close a parent issue I should not have to remember how long I have spent on all its subtasks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lee,
The time spent that you logged on the sub tasks will be added to the total Logged time (the 3th bar in the above example). It will not be deducted from the Estimated Time (1st bar in the example) logged on the parent, this is not how this functionality behaves.
Some more information can be found here : https://answers.atlassian.com/questions/28328/jira-and-sub-tasks and here : https://confluence.atlassian.com/display/JIRA/Logging+Work+on+an+Issue
Best regards,
Peter
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
aH, if I close the task manually it lets me do it without updating the time spent on the parent task. However if the last subtask is completed it springs up a screen asking to close the parent task and will not let me close it without manually entering a time spent....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Peter,
If we remove the effort from the main top-level task or story, it then shows no estimation on the planning board lines. Shouldn't it show the overall estimation (including sub-tasks) even when the parent line effort is empty at planning mode?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey admins! I’m Dave, Principal Product Manager here at Atlassian working on our cloud platform and security products. Cloud security is a moving target. As you adopt more products, employees consta...
Connect with like-minded Atlassian users at free events near you!
Find a groupConnect with like-minded Atlassian users at free events near you!
Unfortunately there are no AUG chapters near you at the moment.
Start an AUGYou're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.