The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

JUST STARTING WITH JIRA !! How define workstreams, tasks, subtasks?

Wilson Robayo
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 27, 2024

Hello COmmunity .... My very first day and first project with JIRA.

I want to create a project with 3 workstreams ("WS") ; each WS has several tasks and one task can have multiple subtasks. How can I define that ??

Typical example:

PROJECT= BUILD HOUSE

      WS#1 FOUNDATION

            Task-1 Prepare lot

                     Subtask 1.1: clean the lot

                     Subtask 1.2: put the fence

            Task-2 Remove garbage and debris

                     Subtask 2.1

                     Subtask 2.2

                     Subtask 2.3

        WS#2 CONSTRUCTION OF BUILDING

       

THANK YOU !!!!!!!!   

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Arun Unnikrishnan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
February 27, 2024

@Wilson Robayo 

A very simple approach would be Theme < EPIC< Story or Task <Sub-task

Theme - Building the house

Epic - Foundation

Story/Task - Prepare a Lot

Sub-task - clean the lot

Screenshot 2024-02-27 144643.png