JQL query is returning a list of issues with values in originalEstimates field.
project = projectname AND sprint = sprint# AND originalEstimate is EMPTY
When I start a sprint, JIRA throws the warning: "Issues nnn do not have a value for the 'Estimate" field. Values entered after the start of the sprint will be treated as scope change'
I do not want the burndown to have problems since the board is configured to Remaining Estimate and Time Spent.
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
As far as I understand the JQL query with the originalEstimate is EMPTY returns tickets with the originalEstimate field set to a value. If so, reindex your Jira.