Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Is it possible to link issues with no dates?

Hi,

I want to create a roadmap/timeline for my project, but future activity issues have no dates, so I am not sure if I can create the dependency if the successor task has no defined start or end date - Is this possible? If so, how?

Thank you!

1 answer

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Sep 29, 2023

Hello @jaime_gilmartinez 

Are you using an Advanced Roadmaps Plan? If so, this appears to work for me.

Click on the + at the end of the time bar for the predecessor task.

Screenshot 2023-09-29 at 2.36.32 PM.png

That brings up the dependency pop-up. 

Screenshot 2023-09-29 at 2.38.18 PM.png

In the Choose an issue... field choose or type in the issue key for the successor task. My environment allows me to enter/select a successor task that has no dates.

Then click the checkmark button.

Screenshot 2023-09-29 at 2.40.07 PM.png

 

You won't see a dependency line because the successor task has no dates, but you'll see the dependency symbol in the predecessor task.

Screenshot 2023-09-29 at 2.42.23 PM.png

 

If you subsequently enter a start date for the successor task, then the line will appear.

Screenshot 2023-09-29 at 2.44.10 PM.png

Hi Trudy,

Thanks for your response. What if the predecessor does not have dates either? In my case, the successors (multiple) concatenate so the very first issue does have a date but the following (which also need linking to each other) don't.

In other words, how do I then link the second task above to a third task, also with no dates?

Thank you

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Sep 30, 2023

Hello @jaime_gilmartinez 

Yes, you can still add the dependency, but not from the Plan.

You need to go to the predecessor issue and add a Linked Issue, setting the relationship to the one you see in the Plan when you create a dependency.

In the backend the dependency is represented as a Linked Issue relationship. You can create the links directly in the issue details screens.

Great, thank you Trudy!

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 01, 2023

Glad to help.

If your questions have been satisfactorily answered please consider clicking on the Accept Answer button.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Site Admin
TAGS
AUG Leaders

Atlassian Community Events