Is it possible to enable "Original Estimate" while creating a issue

Batuhan Dogan April 6, 2023

Screenshot 2023-04-06 at 3.47.31 PM.png

We'd like to add the "Original Estimate" field, while creating a issue type. Currently it's only visible after the creation of an issue type. 

Active Sprints -> Board Settings -> Estimation - turning on this setting still won't help me resolve this issue. Any other ideas?

2 answers

1 accepted

0 votes
Answer accepted
Troy Anderson May 3, 2023

Original Estimate can only ever be part of the Context Fields  (i.e. Details) section.  Context Fields are defined as "secondary information that your team might need to sort, filter, or report on issues".  Original Estimate is not secondary information.  But, on the bright side, it will remain visible no matter which issue tab or view you are on.

Mikael Sandberg
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 3, 2023

Not true, the original estimate can be on the create screen too, you just have to add the time tracking field to the create screen and you will see Original Estimate when creating the issue.

Like # people like this
3 votes
Mikael Sandberg
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 6, 2023

All you have to do is add Original estimate to your create screen. Just go to Project settings > Screens, select the screen used by the issue type you want to change and then add the field to the Create screen.

Screenshot 2023-04-06 at 1.02.47 PM.png

Batuhan Dogan April 6, 2023

Do you mean add it from Field Tab? Because it's not popping up

Screenshot 2023-04-06 at 4.17.35 PM.png

Mikael Sandberg
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 6, 2023

My bad, you need to add Time tracking to the screen, that will add the original estimate field.

Screenshot 2023-04-06 at 2.47.32 PM.png

Like # people like this
Batuhan Dogan April 7, 2023

Thanks for the help Mikael, this issue has been resolved.