Can anyone please point me in the right direction if this is achievable?
I am trying to create an automation that moves all linked epics forward or backward when an epic due date changes but I only managed to get it working with a direct linked epic. Please see screenshot for further clarification.
{{issue.duedate.plusDays(fieldChange.to.toDate.diff(fieldChange.from.toDate).days.abs)}}
{{issue.duedate.minusDays(fieldChange.to.toDate.diff(fieldChange.from.toDate).days.abs)}}
Hi @Vidhya Kumar - have you selected this option under rule details, to allow the rule to trigger after it updates the due date for epics linked from the first epic?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for creating the rule. It helps me for planning the project. But Jira create loops, when the automaion rule works.
Do you know why?