Hello, i hope you can help me and understand my English :D

We have Requirement Tickets. Under that Required Tickets there are Feature Tickets, To Do Tickets and Bug Tickets (depends all on the Requirement Ticket).

Now i want to summarize up the Time of all that tickets in the Feature Ticket.

Is that possible and how do i implement that?

Thank You First :)

Thomas

1 answer

0 votes
Tanner Wortham
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 8, 2013

If I understand your situation, it's as simple as clicking a checkbox. All hours from sub-task roll up to its parent. Simply click the "Include sub-tasks" box in the "Time Tracking" section.