How to show "Due date" field in the card layout in a Kanban board from a Company managed project?

Marina Ballester Ripoll December 29, 2022

Hi,

I am trying to show the 'Due date' field on the cards from a specific Kanban Board from a Company Managed software project but for some reason I am not able to make it work. Below I explain the steps performed:

1. Click on 'Board settings'

2. Click on 'Card layout'

3. In the dropdown menu, search for 'Due date' field and click on 'Add' (please see below image):

Captura.PNG

 

However, when I go back to the Kanban board after performing the above steps, I still do not see the Due date on the cards as you can see in the image from below:

2022-12-29 13_26_14-Window.png

 

Even if the field 'Due date' is fulfilled:

Captura.PNG

Can you please help me add it?

Thanks!

2 answers

1 vote
Dave Mathijs
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 29, 2022

Hi @Marina Ballester Ripoll welcome to the Atlassian Community!

When you go to the issue detail view, is the Due date actually filled out? If you fill it out, does it appear on the card on the kanban board?

John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 29, 2022

That was my question - is there actually a value in the field for it to display.

Marina Ballester Ripoll December 29, 2022

Yes, the 'Due date' field is fulfilled for all of them, here you can see the detailed view of the card shown on the left side:

Captura.PNG

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
December 29, 2022

Hello @Marina Ballester Ripoll 

It is possible that there is more than one field named "Due date" in your instance.

You can determine this by going to the Advanced Issue Search screen, switching to JQL mode, and typing in Due in the JQL field. A list of all possible matching fields will display.

You should see only this

Screen Shot 2022-12-29 at 8.53.25 AM.png

If you see another entry that says Due date then you have more than one Due Date field in your system. In that case you should work with your Jira Administrators to see if the additional Due Date field can be eliminated or renamed.

Marina Ballester Ripoll January 2, 2023

Hi @Trudy Claspill

Many thanks for your message. I have checked what you said and indeed, I can see more than one 'Due date' field:

Captura.PNG

However, when I look for the 2 'Due date' fields in Project Settings > Issues > Fields and I sort them alphabetically, I can see only one:

Captura.PNG

Also, when I look for the 'Due date' field in the Cards Layout configuration in order to see if both appear so that I could switch to the other one, again, only one is appearing: 

Captura.PNG

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 2, 2023

Provide the information you found to your Jira Administrators. Ask if they can temporarily change the name of the custom field named "Due Date" to something else to see if that makes a difference in what you see available for Card Layout options.