Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,558,161
Community Members
 
Community Events
184
Community Groups

How to re-use epics between team-managed projects

Hi everyone,

our epics are defined from a business perspective. We need multiple teams to implement them.

  • How could we re-use those epics between team-managed projects?
  • How could we even re-use those epics between team-managed and company-managed projects?

Thanks in advance & Kind regards

Ralf

1 answer

1 accepted

0 votes
Answer accepted
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Jul 05, 2021

I don’t understand what you mean by reuse an epic. Epix or issues that contain stories or tasks. You can continue to add stories or tasks to your epic as long as you like. An epic can have stories/tasks from multiple projects in CMPs.

CMP = company managed projects?

My question relates to team managed projects. 

Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Jul 05, 2021

Sorry, your second bullet mentioned CMP as well. My poin is that while you can have an epic within a CMP consist of issues from different projects this is not the case for TMP.

you cannot mix issues from different TMPs under an epic within a TMP

Ivan Akcheurov
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
Apr 21, 2023 • edited

This issue affects me too. We have a TMP with epics. I want to assign issues from another CMP to one of those epics from the TMP. TMP epics don't show in `Epic link` field of CMP issues.

Is there a bug/feaure request for this?

CMP = company managed project.
TMP = team managed project.