is it possible to customize the Version report to the number of completed stories instead of story points?
In the documentation in the link given under it says that it is possible to choose the estimation statistics.
"The graph shows the state your version was in at any given point in time, in terms of your total and completed Story Points (or other Estimation Statistic of your choice)."
Or how is it possible to customize the version report graph in terms of other estimation Statistic?
Hello @Jelena Nikolic
Welcome to the community.
That is a reference to the Estimation Statistic that is chosen in the Board Settings/Estimation page of the Scrum board associated with the project. If you change the configuration for the board, that will be reflected when looking at the reports associated with that board.
Hi @Trudy Claspill
thank you very much for the answer, it was very helpful!
Jelena