How to cancel a story in Jira

Hello

Currently my story workflow is as follow: 

To Do => In progress => Done

I want to add another end status which is "Cancelled", so i can move the story from To Do or In progress to Either "Done" or "Cancelled". I want to have the following option in my Workflow:

To Do => In progress => Done

To Do => Cancelled 

When i tried to add cancel status, it is added as middle status, even when i moved it through the board , i couldn't manage to branch (split) the end status to either Done Or Cancelled 

 

Thanks for your help in advance. 

2 answers

I like the first solution better. Here's a walkthrough for the newbies like me :

  • Open your workflow : Issues > Workflows > Choose your workflow and click Edit
  • Add a new status and check the box "Allow all statuses to transition to this one"
  • In text view, edit the transition to the new status, for exemple Cancelled (51) >> Cancelled
  • Add a post function to change the resolution. Post Function > Add post function > Update issue field > Add > and change issue field to "Resolution" and Field value to "Won't do".

Wery nice answer it helps me. And I spend some time t find it. Maybe my flow helps someone too.

  • project settings
  • workflows-> (edit pen sign)
  • Diagram -> add status -> move it on diagram under in progress
  • Click on Text near Diagram -> Click on Cancelled -> the same -> post function
    post function could be not editable look above you should see notification "You are editing a draft workflow"
0 votes
Jack Brickey Community Leader Oct 29, 2019

There are two ways to do this:

  1. Create a new Cancelled status w/ a Done Category and set up the transitions as desired. Likely just use "All".
  2. Create a Cancelled Resolution and continue to use Done but set the Resolution to Cancelled when you cancel a request.

Generally I like #2

If you need detailed assistance LMK.

Hi, 

Thanks for the response, it is very helpful, however I have a problem: I would like to apply the first way, but my JIRA instance has the message like <<You can only have one "Done" status.>> Do you know why?

 

image.png

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Published in Apps & Integrations

🍻🍂Apptoberfest Update: Upcoming Virtual Events 🎉

Hello Community! I hope you've been enjoying the 🍂Apptoberfestivities🍂 (I know I have!) The event is heating up next week with a series of virtual events that we're calling the 🍻🍂Partner App ...

78 views 1 6
Read article

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you