Hi,
What is the correct way to add a "Resolve Screen" transition screen to an active workflow? The workflow currently has 5 statuses that have global transitions enabled. I'm guessing "All" means each status can transition to any other status moving forward or backwards.
Here is where my questions comes in. How do I add a "Resolve Screen" transition screen between "In Progress" to "Done" without it creating a second "Done" on the task screen? I suspect it's because there's already a global transition but I don't know the correct steps for replacing the global transition between "In Progress" to "Done" with my 'transition screen' transition without breaking anything connected. What should I check beforehand?
Any insight would be greatly appreciated!
@JRodney Estrada - steps for replacing the global transition between "In Progress" and "Done" would be to:
(Since you still have "All" transitions on the other statuses, users can still "undo" an issue's status to an earlier one if they mess up.)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@JRodney Estrada - no problem - hopefully that does the trick!