Task A is completed on September 15th. Which formula do I need to use to set the due date of Task B 5 business days after?
Thank you,
Dominique
Hi Dominique - Welcome to the Atlassian Community!
You would start with an automation rule with a trigger of Issue Transitioned to Done.
There needs to be some type of linkage between the issues. Once you identify that with a Branch, you would do a new action of Edit Issue and select the Due Date.
Then in that field you could use the formulate of:
{{now.plusBusinessDays(5)}}
would task B be something that you can define with rules (only child of A, linked to A throug a specific linktype, some specific value in a custom field...) or just a hand picked issue?