How do I move stories into a next generation project completed sprint?

John Hart August 14, 2019

I closed a sprint and all of our Done stories moved into the new sprint. I want to move these Done stories into the sprint that we just closed. How can I do this?

2 answers

1 accepted

0 votes
Answer accepted
John Hart August 30, 2019

At this point next-gen projects don't support parallel sprints, so the option posted by Angélica Luz does not apply to this case. Atlassian has feature requests suggesting the ability to edit closed sprints and also for parallel sprints:


https://jira.atlassian.com/browse/JSWCLOUD-17195
https://jira.atlassian.com/browse/JSWCLOUD-17208

0 votes
Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 16, 2019

Hi John,

Welcome to Atlassian Community!
Currently, it's not possible to make changes to a closed sprint, so, in this case, you can reopen the sprint to add the stories and then complete it again.
Just make sure that all the stories are on the last column and that the resolution is set.
- Reopening a sprint

Regards,
Angélica

John Hart August 28, 2019

Your advice is contradicted by the apparent inability of Jira to support parallel sprints in next-generation project which according to your documentation is required in order to be able to reopen a sprint..

https://confluence.atlassian.com/jirasoftwarecloud/reopening-a-sprint-785332001.html?_ga=2.134212814.1560036806.1567016450-2042519882.1566927910#

but according to a community thread where you posted:

  • As we can see on Jira SW Roadmap, parallel sprints are not supported for now.

https://community.atlassian.com/t5/Next-gen-questions/next-gen-board-parallel-sprints-not-available/qaq-p/907527

 

Just for clarity, I have permission to manage sprints...

Angélica Luz
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 30, 2019

Sorry for the misunderstanding. Indeed next-gen doesn't have parallel sprints, so the option I posted is not applied in this case.
We have a feature requests suggesting the ability to edit closed sprints and also for parallel sprints:
- https://jira.atlassian.com/browse/JSWCLOUD-17195
- https://jira.atlassian.com/browse/JSWCLOUD-17208

Suggest an answer

Log in or Sign up to answer