How do I move my incomplete tasks from Sprint n to Sprint n+1, yet preserve the basline for Sprint n

If I am moving the incomplete task of Sprint n to Sprint n+1, I am losing the baseline(estimated effort, graph of estimated vs actual) which was created with Sprint n.

Example: At the beginning of the sprint, User Story  8 story point. Has 4 sub-tasks. Each of duration 2days each.

At the end of the sprint, 4 story points are completed. 2 sub-tasks are completed. 2 subtasks are incomplete. Now if I move 2 subtasks to Sprint n+1. I loose the baseline history of Sprint n. 

There should be a way to preserve the history of Sprint n and continue the remaining tasks in Sprint n+1.

Have not able to figure it out yet. Have anyone come accross this issue?

Regards

Abhi

0 answers

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

938 views 5 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot