How do I move my incomplete tasks from Sprint n to Sprint n+1, yet preserve the basline for Sprint n

If I am moving the incomplete task of Sprint n to Sprint n+1, I am losing the baseline(estimated effort, graph of estimated vs actual) which was created with Sprint n.

Example: At the beginning of the sprint, User Story  8 story point. Has 4 sub-tasks. Each of duration 2days each.

At the end of the sprint, 4 story points are completed. 2 sub-tasks are completed. 2 subtasks are incomplete. Now if I move 2 subtasks to Sprint n+1. I loose the baseline history of Sprint n. 

There should be a way to preserve the history of Sprint n and continue the remaining tasks in Sprint n+1.

Have not able to figure it out yet. Have anyone come accross this issue?

Regards

Abhi

0 answers

Suggest an answer

Log in or Sign up to answer
Atlassian Community Anniversary

Happy Anniversary, Atlassian Community!

This community is celebrating its one-year anniversary and Atlassian co-founder Mike Cannon-Brookes has all the feels.

Read more
Community showcase
Sarah Schuster
Posted Mar 28, 2018 in Jira Software

Can a company’s culture make or break agile adoption?

Can a new-to-agile team survive and thrive in a non-agile culture? If so, what advice would you give to those trying to be agile in a non-agile culture? What's the key(s) to success? Share your thoug...

11,966 views 15 13
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you