How do I move my incomplete tasks from Sprint n to Sprint n+1, yet preserve the basline for Sprint n

If I am moving the incomplete task of Sprint n to Sprint n+1, I am losing the baseline(estimated effort, graph of estimated vs actual) which was created with Sprint n.

Example: At the beginning of the sprint, User Story  8 story point. Has 4 sub-tasks. Each of duration 2days each.

At the end of the sprint, 4 story points are completed. 2 sub-tasks are completed. 2 subtasks are incomplete. Now if I move 2 subtasks to Sprint n+1. I loose the baseline history of Sprint n. 

There should be a way to preserve the history of Sprint n and continue the remaining tasks in Sprint n+1.

Have not able to figure it out yet. Have anyone come accross this issue?

Regards

Abhi

0 answers

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,033 views 7 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you