How do I get a report of the % completed story points for all epics

I know I can hover over the progrsss bar in each epic and it will tell me % complete x story points complete out of y

Is there a way to get this from a query so we can roll these up in excel across the org.

1 answer

0 vote
Ahmad Danial Atlassian Team Apr 29, 2013

Hey there, Bernard.

Apart from the default reports that are being offered by GreenHopper (https://confluence.atlassian.com/display/GH/Using+Report+Mode), you might want to look into customization or perhaps a report-related third party plugin that might be able to cater for your requirement.

SQL query might help but I do feel that it is pretty complex. Perhaps others can share their thoughts on this too?

Warm regards,

Danial

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,032 views 7 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you