How do I change Sprint dates?

Carol Rigdon
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 17, 2020

I started the sprint and immediately noticed that the dates are wrong. How do I updated them? Using jira server.

 

1 answer

0 votes
Earl McCutcheon
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 19, 2020

Hello @Carol Rigdon ,

Thanks for reaching out, and details on editing a sprint can be found in the following documentation for a referance point under the section "Editing, reordering, or deleting a sprint":

And the Sprint start and end dates can be modified after starting the sprint by navigating to the backlog and selecting the three dot menu icon to the far right side opposite fromt he sprints name and choosing "Edit Sprint":

Screen Shot 2020-05-19 at 3.10.41 PM.png

It will give you the following popup to make the desired modifications:

Screen Shot 2020-05-19 at 3.10.58 PM.png

Also do take notice of the note mentioned in the documentation in this section:

Note: You can only edit sprints that have not been completed yet. Also, the date fields are not specified until you start a sprint.