How can I use a smartvalue to calculate the date in a custom field + 6 business days?

Gabriel Viger January 13, 2021

Hello everyone,

I am trying to create an automation rule where it calculates the date from a custom field plus 6 business day.

I have looked at the documentation and found this smartvalue but I don't know how to take the source date from a custom field rather than "now":

{{now.plusBusinessDays(6)}}

Would it be {{(issue.customField_xxxxx.value).plusBusinessDays(6)}}?

Thanks for the help everyone! :)

Gabriel

1 answer

1 accepted

0 votes
Answer accepted
John Funk
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
January 13, 2021

Hi Gabriel,

Try this:

{{issue.customField_xxxxx.plusBusinessDays(6)}}

Gabriel Viger January 14, 2021

Hi John,

Ok I will test this as soon as I can and let you know if it worked.

Thanks for the help :)

Gabriel

Like John Funk likes this
Gabriel Viger January 19, 2021

Hi John,

it worked.

Thanks for your help :)

Cheers,

Gabriel