I left my office Friday, forgetting to close my sprint for the week. Is there a way to edit the end date/time of the sprint in order to correct my burndowns & statistics?
Hi Matt, as far as I can tell, the only way to change the end date is directly via database (table AO_60DB71_SPRINT), however you may consider testing it first in a test environmnet.
Cheers
Is it possible to access the database for an atlassian-hosted Jira Agile account?
Hi Matt, OnDemand customer don't have access to the database
Updating the END_DATE in that table did not work for me. What other tables might I need to update?
I am assuming by END_DATE you mean COMPLETED_DATE and not the last day of the sprint as defined when the sprint was originally set up. AKA - start and two weeks later end... The COMPLETED_DATE is the date when you hit "Complete Sprint"
Hey Matt,
This is absolutely achievable without DB manipulation - at least in the current version.
All you need to do is go to your sprint report, find the sprint you wish to edit via the drop down menu. Once you have that selected there's a more options / kabob menu icon (3 horizontal dots) which will allow you to reopen that sprint. At this point you can then visit your backlog and change the dates of the sprint and then re-close.
Your current sprint (if you have one active), will remain unharmed, unedited and can continue to feature in active sprint view, upon the close of retro-active sprint.
Thank you
Thanks! You helped me a lot!
I think this misses the point. You can edit the END_DATE like this, but you will also cause the COMPLETE_DATE to be changed to the date/time that you re-closed the sprint after performing this edit, which is even later than the date on which the sprint work was actually terminated. It is the COMPLETE_DATE that affects your analytics (as mentioned by Dave Thomas) and i think the END_DATE just represents your original plan. Once the sprint is finished, the END_DATE is just window dressing.
It looks like you're new here. Sign in or register to get started.