How can I add time time tracking details to my sub tasks on Rapid board

To make our stand ups more streamlined we'd like to be able to log time on sub tasks directly from our rapid board. How can I add this functionality? All that is currently displayed on the sub task card is summary and priority.

1 answer

1 accepted

In the 'estimation' tab on the board configuration set the board to use 'Original Time Estimate' for the estimation statistic and 'Time Tracking' on.

Then in the board, if you click on the sub-task the detail view will open. In work mode on the detail view hit the '+' sign next to the remaining estimate lozenge to log work.

Thanks,
Shaun

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Jan 29, 2019 in Jira Software

Transforming Jira Software projects for general project management purposes

...It's true that there are projects in Jira; but they are merely a way to cut off issues, to tell them apart from other sections of work and to apply rules that are specific to that team (the schemes)....

183 views 0 6
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you