How To Edit Subtask Estimate & show Correct Remaining Values

Rita Arellano
Contributor
August 19, 2022

Hi,

 

I am so new to automation. So our team uses estimates in time and not story points - not my choice, but that’s the way it is.

I was able to successfully automate estimates from subtasks and have them roll up to the story. 

I also was able to automate the remaining value when time is logged correctly.

 

What I can’t do is let’s say subtask estimate is updated - for example, subtask  was 5 hrs. Then I realized it’s 6 hrs to do the subtask. My remains value still shows 5 hrs. instead of 6 hrs.

 

how can I fix this? 

 

 

 

 

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 20, 2022

You will need your automation to run on any change to the estimate field on every issue or sub-task.

I would not bother doing this though.  If you're using the time-tracking for the estimates, then Jira already does this for you - look at the time tracking panel on the issue and you'll see it includes the estimates on the sub-tasks (and there's a tick box to toggle between "include sub-tasks" and "this issue only".

Oh, and it breaks Scrum and Kanban if you are using them.