Help me understand Time Tracking Report (Accuracy)

Sebastian Somi March 29, 2023

Hi, 

I understand that for the top column the accuracy of -1d3h is result of 1d estimate - 2d 3h time spent.

 

What is the logic behind the bottom red rectangle?

 

Because - 5h does not equal 4h original estimate - 6h time spent.

 

image.png

1 answer

0 votes
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 29, 2023

Hi Sebastian,

It takes into account the estimate of the time remaining too.

In this case, you have:

  • Original estimate: 4h
  • Time remaining: 3h
  • Time spent: 6h

It's a bit convoluted, but think of it as

We've done 6 hours on it, we've got 3 remaining, so the estimate-to-complete is now 9 hours. 

We originally estimated 4 hours, so 9-4 = an underestimate of 5 hours.