Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,560,386
Community Members
 
Community Events
185
Community Groups

Edit Priority of a Sub-Task in Sub-Task table

Sub-Tasks are displayed in a table in the parent task. In this table it is possible to change the status of the sub-task. Changing the priority of a sub-task isn't possible, for that I have to open the sub-task to do so.

Is there an option or configuration where I can set the priority field editable in the sub-task table.

2 answers

Are there any updates on this?  I've come up with the same problem, but it's unclear if this ever got solved or led to a feature request

0 votes
Ismael Jimoh
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 27, 2019

Hi @Admin 

The edit issue is needed for what you described even when you edit from the screen. Hence, check if edit is qn option.

If it is not, raise a feature request with Atlassian at jira.atlassian.com if auch a request does not already exist.

The only other way I know of is adding a transition back to itself with a screen that lets the user set the priority again. This is transition will be available in the options of the parent issue.

Cheers