Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,558,943
Community Members
 
Community Events
184
Community Groups

Does native Jira support dynamic project scheduling and resource management?

We have adopted the Jira platform as our company seeks to adapt a more agile methodology, however we will initially need to support waterfall projects. Does native Jira support dynamic scheduling. Will dependencies adjust the start and due dates? Will a percent complete be calculated by comparing the time entered by resources to the anticipated work effort? Or is percent complete calculated by it's position in the workflow?

Can a resources complete utilization on projects be calculated to show their availability for future work, and can a resource be allocated to a project for a percentage of time and not full time? Can multiple resources be assigned to the same task. 

We have been doing dynamic scheduling and resource management in MS Project Server, and would like to provide that capability to project and resource managers now, and for the short term, until we adapt a more agile approach.

Our organization is somewhat frugal, and would like to do as much as we can in native Jira, but if that's not possible, some add-in suggestions and/or articles that address this topic would be greatly appreciated. 

Cheers, Ray 

1 answer

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Mar 20, 2023

Hello @Raymond J Wohltman 

Have you subscribed to Jira's Standard plan or Premium plan?

The Standard plan (for the Jira Software product) includes Basic Roadmaps, while the Premium plan includes Advanced Roadmaps. For an overview of the differences in the Roadmaps functionality take a look at this page.

As per that page a Capacity Planning feature is available only with Advanced Roadmaps which is available only with the Premium plan.

I have not worked with the features in detail, so I can't really provide much in the way of details particularly about capacity planning.

Thanks! We do have Premium, but no add-ins. I'm ideally looking for a way to create a project schedule using a WBS that allows me multiple levels of task hierarchy, and when one task's due date / finish date is extended, it dynamically adjusts its dependencies. Detailed and dynamic project scheduling.

Cheers, Ray 

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Apr 03, 2023

Have you reviewed the Auto-scheduling functionality in the Advanced Roadmaps feature?

https://support.atlassian.com/jira-software-cloud/docs/how-does-the-auto-scheduler-in-advanced-roadmaps-work/