Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Display of the Target Start and End dates on Timelines in JIRA

Hello is there a way to display the Target Start and End Dates for Features (Issue Type in JIRA) and also on the same board have the Sprint View for the Stories?

 

 

1 answer

0 votes
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 12, 2023

Hello @Angana Patel 

If you are referring to the Timeline feature available in the left-side navigation panel for a board, it is not possible to add more fields to the display of that feature, nor change the time bars to use different fields. The time bars are locked into using the Start date and Due date fields.

But I have seen the Stories appear as Sprints. 

I wanted to JIRA_Timeline.PNGNeed to know how to make the Feature issue type configured to the Start and End date. 

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Oct 12, 2023

In the basic Timeline feature you can see that the Feature issue type is considered a child issue of the Epic.

In the basic Timeline feature you can display the time bars for child issues using either the Start date and Due date fields, or you can display the time bars for child issues based on the Sprints to which they are assigned. You can't have both.

Like Angana Patel likes this

Thank you for your inputs