Deleting or reducing logged time

Patrycja Helbin
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 4, 2023

Hi,

 

I have a problem with the remaining estimate calculation done by JIRA. When task have 3 days original estimate, the time spent is already 2 days and I delete 1 day from time spent the remaining estimate is changing to original estimate + deleted time. In this case insted of 2 days in remaining estimate I have 4. Do you have any other notification about it?

 

Best regards,

Patrycja Helbin

1 answer

1 accepted

0 votes
Answer accepted
Dave Liao
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 14, 2023

@Patrycja Helbin - hi Patrycja!

Have you seen this help doc?

https://support.atlassian.com/jira-software-cloud/docs/log-time-on-an-issue/

[when deleting a time log] You'll be asked whether you'd like to adjust the remaining time estimate. If you choose to adjust it, you can let Jira automatically adjust the time remaining by adding back the deleted time or set it to another time manually.

I think that's what's happening to you?

Let me know if you're still encountering this issue!