I have a SCRUM board where the time tracking has been enabled. The red line (progress of remaining estimate) only displays the remaining estimal of the parent issue (the User Story) and not the sum of remaining estimals including subtasks. 

In the user story view, I can see that the sum is correct if I include sub tasks.

Did I miss a configuration?

Thanks

1 answer

0 votes

Hi Stephane,

This has been addressed in other posts.  For a good explanation please see the Communities post burndown chart to show story points from sub-task (or technical task)?

In addition, if you believe JSWSERVER-10266 addresses the issue you're running into please vote on it to add impact!

Cheers,

Branden

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

709 views 5 16
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot