Burndown calculation (jira agile)

Hi All

I have a query on burndown calculation on jira agile.

If i move an issue to the right most column (say Done) does that mean that burndown will burn down all remaining estimate irrespective of the fact whether there is remaining estimate left on an issue?

PS: I using estimation statistic as original time estimate and time tracking as remaining estimate and time spent.

Rahul

2 answers

1 accepted

I have checked burndown does not automatically burndown the remaining estimate to zero when you move it to the done column.

0 votes
Timothy Chin Community Champion Mar 27, 2014

If i move an issue to the right most column (say Done) does that mean that burndown will burn down all remaining estimate irrespective of the fact whether there is remaining estimate left on an issue?

I believe yes. Since the most right column is considered "complete". The easiest way to check is to create a test project and some test issues to test it out.

Suggest an answer

Log in or Join to answer
Community showcase
Teodora [Botron]
Published Thursday in Marketplace Apps

Jira Inferno: The Nine Circles of Jira Administration Hell

If you spend enough time as a Jira admin - whether you are managing a single, mid-sized instance, a large enterprise one or juggling multiple instances at once - you will eventually find yourself in ...

240 views 0 11
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you
Atlassian Team Tour

Join us on the Team Tour

We're bringing product updates and pro tips on teamwork to ten cities around the world.

Save your spot