Burndown calculation (jira agile)

Hi All

I have a query on burndown calculation on jira agile.

If i move an issue to the right most column (say Done) does that mean that burndown will burn down all remaining estimate irrespective of the fact whether there is remaining estimate left on an issue?

PS: I using estimation statistic as original time estimate and time tracking as remaining estimate and time spent.

Rahul

2 answers

1 accepted

I have checked burndown does not automatically burndown the remaining estimate to zero when you move it to the done column.

0 vote
Timothy Chin Community Champion Mar 27, 2014

If i move an issue to the right most column (say Done) does that mean that burndown will burn down all remaining estimate irrespective of the fact whether there is remaining estimate left on an issue?

I believe yes. Since the most right column is considered "complete". The easiest way to check is to create a test project and some test issues to test it out.

Suggest an answer

Log in or Sign up to answer
How to earn badges on the Atlassian Community

How to earn badges on the Atlassian Community

Badges are a great way to show off community activity, whether you’re a newbie or a Champion.

Learn more
Community showcase
Published May 21, 2018 in Jira Software

How large do you think Jira Software can grow?

Hi Atlassian Community! My name is Shana, and I’m on the Jira Software team. One of the many reasons this Community exists is to connect you to others on similar product journeys or with comparabl...

1,206 views 10 18
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you