BurnDown chart with its own statuses

Olga August 26, 2022

Our workflow:
TO DO - IN PROGRESS - PAUSE - PRETEST - TESTING - DONE

Tasks in the status PRETEST, TESTING and READY are considered as finished by us

Снимок экрана 2022-08-26 145643.png

We know. that the sprint burndown chart considers a task to be ready only if it is moved to the last right column. If it is possible to set up a diagram so that it takes into account tasks as solved in the status PRETEST, TESTING, READY?Снимок экрана 2022-08-26 145902.png

Our project is managed by a team.

1 answer

1 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 26, 2022

Welcome to the Atlassian Community!

No, the diagram reflects the same data as the board does.  To get it to see your not-done issues as done, you need to map the status into the last column.

Olga August 26, 2022

Okay, is it possible to solve this problem with the help of third-party applications?

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 26, 2022

What problem?

The burndown chart is showing you what you have completed, as you completed it, as is the board.  I am not sure what else you might expect?

Olga August 28, 2022

We would like to build a diagram for our readiness statuses - PRETEST, TEST, READY

Perhaps there is another solution for compiling such a diagram, we just do not see it or do not know it. We have not been using Atlassian products for a long time, and we may misunderstand something.

Nic Brough -Adaptavist-
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 29, 2022

I thnk you have, yes.  Burndown charts show you the burndown for a sprint, in a Scrum methodology.  

The chart you are asking for is not a burndown chart, so the scrum tool doesn't have one.

It's not a problem that you're not doing scrum, but you can't expect a scrum tool to support your not-scrum process.

You will need to look to adding apps that can give you the (not burndown) reports that you're looking for.