My Business Unit has a Project Board covering our entire backlog, but have 4 agile teams working on the epics and stories within it.
I want to be able to produce separate Burn Down Charts for each team (named Magenta, Blue, Green & Red. These are set up in the Quick Filters and work fine when viewing the Backlog and Active Sprints
The Burn Down chart documentation states that the report is specific to a Board and the active filters applied to it.
However, when I click on reports a Burn Down chart appears showing all user stories for all teams and seems to ignore the filters. There is no option to apply a filter within the report.
Have I misinterpreted the documentation or can this be done?
Any help would be much appreciated
Cheers
If you want separate burndowns you must have separate boards. the burndown chart is not effected by quick filters. Unless of course something has changed in newer versions which is certainly possible.
Hi @Andrew Carroll,
Welcome to the community!
Let's work through this together. What type of project are you using. In the documentation here:
https://confluence.atlassian.com/jirasoftwarecloud/burndown-chart-777002653.html
there are different steps for the scrum/kanban projects than there are for agility/featured projects.
Can you please tell me whether you are using cloud or server and the project type?
Hope I can help!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Patrick,
Thanks for the quick reply.
our JIRA install is server based and the project type is Software
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ok @Andrew Carroll,
Which Jira version are you using?
Do you have separate boards set up for each team?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you need to break into four boards. can you share where you might be reading that the quick filters influence the burndown chart?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jack, That's a bummer, I was hoping to be able to keep the Project and Backlog as a "Global" view whilst seeing the reports at a team level. We'll have to review how we would like to organise our work.
The specific mention of filters for Burndown Charts was on the Documentation page here https://confluence.atlassian.com/jirasoftwarecloud/burndown-chart-777002653.html?_ga=2.49798822.1210751781.1534946246-663555643.1511341513
First bullet point under Understanding The Burndown Chart, although it didn't refer to Quick Filters
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What @Jack Brickey said above is correct and what I was getting to, albeit a bit slower :)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Andrew, you can have one backlog and general board and 4 scrum boards based on filters just for the Burndown charts