Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Come for the products,
stay for the community

The Atlassian Community can help you and your team get more value out of Atlassian products and practices.

Atlassian Community about banner
4,414,280
Community Members
 
Community Events
170
Community Groups

Automation to set Parent Link for Epic to Initiative

Edited

Fellow Automators,

I am at an impasse with Automation for Jira and need help.

My dept is currently using an automation to create an Initiative (custom issuetype for Adv Roadmaps, heirarchy set up per documentation) for every Epic created in this other project, however, for the sake of the Plans feature, I cannot figure out how to set the Parent Link between the two via Automation.

I saw another discussion give an answer for a Parent Link for a Task using this code "{"fields":{"parent":{"id":"36768"}}}" but this error is returning to me "Issue type 10020 is not a sub-task but a parent is specified. (issuetype), Sub-tasks must be created in the same project as the parent. (project)."

Could this error be because it was for Tasks and not Epics? What would be the correct id?

This area of Automation is lacking and I dearly miss Code Barrell's documentation, but that's another topic.

Thanks for any help yall can provide.

1 answer

1 vote
frother Atlassian Team Sep 28, 2020

Hi Ethan,

Thanks for reaching out.

The hierarchy in advanced road maps unfortunately isn't maintained by a single field, it depends on the issue type.

Epic -> Any issue above epic: Need to set parent link

Any issue -> Epic: Need to set epic link

Subtask -> Any issue: Need to set parent

So with that said, it sounds like you are trying to set a relationship maintained by the parent link field. To do that you need to do the following in the advanced section:

{
"fields": {
"Parent link": "ISSUE_KEY_HERE"
}
}

Hope that helps.

Cheers,
Scott.

Scott, 

By the looks of it, this would be for setting a single issue as parent link. What would be the coding for setting it as the trigger issue.

My Automation goes:

Manual trigger
Clone Epic ticket to be an Initiative ticket in the IN project and set the parent link.

I feel like the documentation has become less useful since Atlassian bought Automation out.

Thanks so much,
Ethan 

Like # people like this

Hi @Ethan V. 

having the same question - could you solve it by now? 

Best,
Jan

Dear @Ethan V. ,

kept searching and found this solution: 

{
"fields": {
"Parent link": "{{triggerissue.key}}"
}
}

In this case the triggering issue is added as the parent, you can change that according to the smartvalue syntax https://support.atlassian.com/jira-software-cloud/docs/smart-values-general/

Best,
Jan

Like # people like this

Hi @Ethan V. , @Jan Stähle  @frother 

 

How would i set the parent link with the attached automation for the EPIC. The trigger issue is service desk issue type, which then creates our ACCOUNT issue type (we renamed the initiative issuetype) and make the ACCOUNT the parent link for the epic. I cant seem to get the above to work and its vital that this automation creates the account as the parent link for the epictempsnip.png

@Ethan V. @Jan Stähle @frother  anything here for my additional inquiry?

Suggest an answer