Automation on Story Point Estimate

u631588 May 18, 2021

Hi, i am trying to automate an update on the field "Story Point Estimate" based on an Rule that trigger a change using a "if-Else" block and and update (based on different conditions that could take a different field that i am using to define a task..)... as I saw, the field "Story point estimate" is not available on the file list, so i need to use an Advance jason... 

Could you tell me if this approach is correct? and how the json should be written?

 

Thanks!!

1 answer

1 accepted

1 vote
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
May 18, 2021

Is this for a Team Managed or a Company Managed project?

I found this post with comments that discuss JSON examples of setting Story Points Estimate in a Team Managed project.

https://community.atlassian.com/t5/Jira-Service-Management/Jira-automation-can-t-find-quot-story-points-quot-field/qaq-p/1471707

u631588 May 18, 2021

Great !

 

Thanks Trudy, i found the solution there.

 

i wrote this rule..

 