The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Automatic subtask status change depending on previous subtask status

Shee Covarrubias
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 9, 2017

I have several projects that we need to have the ability to have a child(subtask) automatically assigned when the preceding child (subtask) is closed/done.  I am unsure how to configure this.  Additionally when the parent (task) is closed I want to be able to configure it so that the next parent(task) is auto assigned and the same with the initial child (subtask)

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 9, 2017

You'll definitely need some coding to do that.  It's not something built into Jira at all.  Sub-tasks are discrete tasks within their parent and have no order or dependency on each other.

I would, as usual, reach for the Script Runner add-on, but there are other scripting and automation add-ons available that might help you.