You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
Hello
I have just started using Advanced Roadmaps in Jira for the past 2 months and created a Roadmap which goes across 4 Jira Projects / Boards. My question is around how the roadmap gets updated. As teams work on their tickets and some items take longer than originally planned, how come the Roadmap doesn't update automatically to reflect the "actual progress"? I may be confused but the only way I see the Roadmap adjusting is if I go in Advanced Roadmap and manually update the dates for the items that have changed. Is this correct or am I missing something? Can you please help clarify how the Roadmap dates should get updated in the plan or do I need to manually update the dates for the epics based on what the development teams are doing real time.
Thanks
- Val
Hi Val,
To show the epics or parent issues dates based on their children, you need to enable Roll-up Dates in your plan View settings. Note that, Advanced Roadmap does not update the epics date fields value in the Jira ticket, but it visualises them in the roadmap and also field sections.
Regards,
Sara