Are you in the loop? Keep up with the latest by making sure you're subscribed to Community Announcements. Just click Watch and select Articles.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Include subtasks not including...

Jira's Time tracking functionality allows users to Log time on an issue which then translates to Time spent or work logged using the units of weeks, days, hours and minutes. This value is paired with the Original Estimate and the Remaining Estimate field that is dynamically calculated using a formula of {Original - Logged = Remaining}.

These estimates can be viewed and calculated directly on an issue or even indirectly if a hierarchy structure is being used, better known as Task (parent) and Subtask (child). Jira is capable of rolling up the Time tracking information from the child level up to its parent, providing a summed total. This is achieved by toggling the Include subtasks checkbox:

2022-12-12_16-02-03 (1).gif

Include subtasks doesn't work for me

The sum of estimates is only available to Task → Subtask relationships, this is to say the parent issue must be a Standard Issue type and the child issue must be a Subtask Issue type of that parent.

Tasks that have a parent are considered Child issues due to the hierarchy structure available in Jira, but they are not the same as Subtasks in nature. This applies to relationships such as:

  • Epic → Story
  • Initiative → Epic

story.png

How do I sum up estimates from Child issues?

While you cannot use the Include subtasks function, it is definitely still possible to get your Child issues' estimates to roll up to its parent. This can be done by utilizing Automation for Jira.

The Community post Sum up logged hours using Automation provides various examples of how to do this since there are many different applications of this workaround. An example rule is also available on our Automation playground and can be used as a reference.

1 comment

Taranjeet Singh
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Dec 20, 2022

Thank you for sharing this article, @Belto ! From my experience, I can tell that this is a very common use case for many organizations using time tracking in Jira and it is great to see that "Automation for Jira" can provide a solution for this.