moving an issue back to backlog with "remove from sprint" functionality.

This question is in reference to Atlassian Documentation: Removing an Issue from a Sprint

Hi, currently when i right click an issue and then press "remove from sprint" this issue is moved to another sprint (let's call it sprint X). i want to change it so that when i choose "remove from sprint" the issue will be moved back to backlog.
where can i change this settings? 

1 answer

Hi,

Removing an issue from a sprint moves it to the next planned sprint, and I don't think you can alter this behaviour. If you want to move the issue to the backlog you can :

  1. drag the issue from the sprint to the backlog in the backlog tab of the board
  2. right click on the issue and select move to top/bottom of backlog (again in the backlog tab of the board)
  3. edit the issue sprint field

Regards,

Peter

Suggest an answer

Log in or Sign up to answer
Community showcase
Posted Oct 09, 2018 in Jira Core

How to manage many similar workflows?

I have multiple projects that use variations of the same base workflow. The variations depend on the requirements of the project or issue type. The variations mostly come in the form of new statuses ...

382 views 6 0
Join discussion

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you