Two Projects, One sprint board - view the cards in sprint for both prjs but not backlog

Sarah April 20, 2020

Hi all,

We are adding quite a few large features to our product.  We have created a couple of new projects (prj 2 & 3) to keep large pieces of work and related stories seperate from our main project (prj 1). 

I have shared the sprint board for Prj 1 between the projects by amending the filter in the sprint board settings to include the new projects, it works well. 

However I can now see all the cards in Prj 2 & 3 in Prj 1's backlog.

Is there a way I can keep Prj 1's backlog for only Prj 1 cards and allow Prj 2 & 3 issues to share the sprint board?

I think the solution is to create an entire new project and sprint board, thoughts please as to a better way.

1 answer

1 accepted

1 vote
Answer accepted
Carlos Garcia Navarro
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 20, 2020

Hi @Sarah ,

You could create a quick filter that filters out the tickets in the backlog for project 2 and project 3 in the backlog. E.g.,

project not in (Project2,Project3) AND status not in ("To Do")

(I'm assuming "To Do" is the status for backlog items only.)

I just tried it in a test scrum board and worked for me.

Hope it helps.

Sarah April 21, 2020

Thanks Carlos, going to try it now.  Will let you know how it goes.

Sarah April 21, 2020

Yay, it worked, thanks so much for your help! 

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events