Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

It's not the same without you

Join the community to find out what other Atlassian users are discussing, debating and creating.

Atlassian Community Hero Image Collage

Jira Cloud - changing dates of closed sprints

Can I change the start/end/complete dates of closed sprint on Jira Cloud? If not can you please confirm when this feature will be available to the cloud instance?

2 answers

0 votes
Luiz Farias Atlassian Team Feb 02, 2017

Hello Robin,

Editing sprint dates are only possible manipulating the information directly on the database.
However, this function is only possible on JIRA Server, since database customization is a restricted function in JIRA Cloud.

Hope these two links help to clarify this matter:

Restricted functions in JIRA Cloud applications

How to edit the Dates Associated with a closed Sprint

Please upvote this related issue https://jira.atlassian.com/browse/JSWCLOUD-16331 so that it can get fixed soon  !!

Suggest an answer

Log in or Sign up to answer
TAGS
Community showcase
Posted in Jira Core

How to manage many similar workflows?

I have multiple projects that use variations of the same base workflow. The variations depend on the requirements of the project or issue type. The variations mostly come in the form of new statuses ...

3,881 views 11 5
Join discussion

Community Events

Connect with like-minded Atlassian users at free events near you!

Find an event

Connect with like-minded Atlassian users at free events near you!

Unfortunately there are no Community Events near you at the moment.

Host an event

You're one step closer to meeting fellow Atlassian users at your local event. Learn more about Community Events

Events near you