Jira Cloud - changing dates of closed sprints

Can I change the start/end/complete dates of closed sprint on Jira Cloud? If not can you please confirm when this feature will be available to the cloud instance?

1 answer

0 votes
Luiz Farias Atlassian Team Feb 02, 2017

Hello Robin,

Editing sprint dates are only possible manipulating the information directly on the database.
However, this function is only possible on JIRA Server, since database customization is a restricted function in JIRA Cloud.

Hope these two links help to clarify this matter:

Restricted functions in JIRA Cloud applications

How to edit the Dates Associated with a closed Sprint

Suggest an answer

Log in or Sign up to answer
Community showcase
Asked Thursday in Jira Ops

I'm John Allspaw, Ask Me Anything about incident analysis and postmortems

I'm John Allspaw, co-founder of   Adaptive Capacity Labs, where we help teams use their incidents to learn and improve. We bring research-driven methods and approaches to drive effective inciden...

2,934 views 8 7
View question

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you