How do I update the subtasks based on the parent issue?

Based on the status of the parent, I want to update the subtasks status.

That is when the parent = "completed" status, the subtasks should be = "completed" as well. Do you know if we can do this without using a plugin?

1 answer

1 accepted

That's not possible without a plugin. The way to do this is to add a workflow post-function to the workflow of the parent issue type which will transition all sub-tasks to "completed".

Here's a sample of how to do this with script runner:

 https://scriptrunner.adaptavist.com/latest/jira/recipes/workflow/postfunctions/auto-close-all-subtasks.html

and a recent related question https://answers.atlassian.com/questions/38745845

There are also other plugins that you can use to achieve the same result.

Suggest an answer

Log in or Sign up to answer
Community showcase
Published Monday in Jira Ops

Jira Ops Early Access Program Update #1: Announcing our next feature and a new integration

Thanks for signing up for Jira Ops! I’m Matt Ryall, leader for the Jira Ops product team at Atlassian. Since this is a brand new product, we’ll be delivering improvements quickly and sharing updates...

357 views 0 8
Read article

Atlassian User Groups

Connect with like-minded Atlassian users at free events near you!

Find a group

Connect with like-minded Atlassian users at free events near you!

Find my local user group

Unfortunately there are no AUG chapters near you at the moment.

Start an AUG

You're one step closer to meeting fellow Atlassian users at your local meet up. Learn more about AUGs

Groups near you