You're on your way to the next level! Join the Kudos program to earn points and save your progress.
Level 1: Seed
25 / 150 points
Next: Root
1 badge earned
Challenges come and go, but your rewards stay with you. Do more to earn more!
What goes around comes around! Share the love by gifting kudos to your peers.
Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!
Join now to unlock these features and more
The Atlassian Community can help you and your team get more value out of Atlassian products and practices.
So I had started the sprint with 22 SP, then after 3-4 days, I moved 1 US worth 1 SP to backlog & added a new US worth 3 SP.
With the above changes, I hoped that after sprint is completed, the 'Commitment SP' would be 22 & 'Completed SP' would be 24.
However, it's showing 'Commitment SP' as 21 & 'Completed SP' as 24.
Can anyone help as to what happened there with the 'Commitment SP'? Why its showing incorrect? Thanks!
@Abhishek Chaudhary - hi Abhishek!
Committed story points will remain unaffected once a sprint starts. From the official docs,
After the sprint has started, any stories added to the sprint, or any changes made to estimates, will not be included in this total.
This makes sense to me, since a team commits (agrees) to a set of work prior to sprint start. This value should remain static.