Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in
Celebration

Earn badges and make progress

You're on your way to the next level! Join the Kudos program to earn points and save your progress.

Deleted user Avatar
Deleted user

Level 1: Seed

25 / 150 points

Next: Root

Avatar

1 badge earned

Collect

Participate in fun challenges

Challenges come and go, but your rewards stay with you. Do more to earn more!

Challenges
Coins

Gift kudos to your peers

What goes around comes around! Share the love by gifting kudos to your peers.

Recognition
Ribbon

Rise up in the ranks

Keep earning points to reach the top of the leaderboard. It resets every quarter so you always have a chance!

Leaderboard

Sprint Start date is exclusive. Can we make it Inclusive?

Hello Community,

I have a problem in counting the working when starting a sprint. When I start the sprint and choose two weeks (starts on monday), the closing date is also on next, next Monday and not friday because the starting date is not included as working day.

Is there any way that the starting date is inclusive?

Any help is very much appreciated!

3 answers

0 votes
Stephen Wright _Elabor8_
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
Mar 08, 2020 • edited

Hi @junnel1001

As far as I can tell, the working days count down to the end of the sprint.

So there are 9 days to count down to the end of the sprint - the last day being "day 0" - you'll notice this on the days left gadget on the dashboard also. This would be based on a 10 day span such as 9th March - 20th March.

Ste

Hi ,

 

Please change the below mentioned time from the screenshot attached

 

Best,

P N B

Hello,

 

It seems I can't find the attachment?

Hi,

Good Day!

Select the Sprint start date as the current date manually(While starting the sprint we can select the start date),which solves your wish.

Hope you understand the concern.

 

Best,

P N B

Thanks for the reply. I can select the start date and end date manually but, it says 9 working days instead of 10 working days, see https://www.screencast.com/t/TUEMD1m7hwM

 

Is there any setting that I can include the start date so that it will be said 10 working days?