Hi Team,

I need to configure two-level cascade select list using JMWE groovy.

We have JMWE plugin only.

let I have two custom field called select1 with value 'Big' and 'Small'

and select2 with values 'A' 'B' 'C' 'D' 'a' 'b' 'c' 'd'

If I select Big from field select1, field sselect2 should populate 'A' 'B' 'C' 'D'

If I select Small from field select1, field sselect2 should populate 'a' 'b' 'c' 'd'

Can anyone please help me? I am not from the development team.

 

Thanks & Regards,

Manzoor Alam

2 answers

1 accepted

2 votes
Answer accepted
Phill Fox
Community Champion
January 10, 2016

As JIRA uses the final column for the "definition of done" and your final column is "Selected for Development" when someone presses the release button it will mark those issues as released that are in that column. JIRA does not realise that this Kanban board is only part of your process. 

The good news is that the release button is only available to people who have project administrator permission so you can remove that permission and that will remove access. 

There is a change in permissions coming that will give you greater control over who can do what on a sprint. See https://confluence.atlassian.com/cloud/blog/2015/11/improvements-to-jira-software-sprint-management and https://confluence.atlassian.com/cloud/blog/2015/11/improvements-to-jira-software-sprint-management to keep an eye on when this is fully released.

0 votes
Deleted user
January 13, 2016

Thanks!