Time remaining

Pierrick JUSSELME
January 17, 2023

Hello,

I don't understand jira remaining time behavior :

In my screenshoot, you can see that i have filled only the "original Estimate" to 22h and save it.

remaining 1.png

But when i go back to edit, the "remaining estimate" has been filled automatically to this value too

remaining 2.png

(And vice-versa => i tried fill to only "remaining estimate" and save. When i go back the "Original estimate" take the value from "remaining estimate")

 

My objective is to have a good chart to help project manager but is not well calculated,

It should be Original Estimate - Logged time = Remaining time

remaining 3.png

 

 

Does someone can  help me, perhaps a configuration mistaken ?

 

Thanks community :)

1 answer

0 votes
Emily Schneider
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
July 31, 2014

Hi Graeme,

The Zephyr issue type Test is still a standard JIRA issue type which means it follows the same rules as other JIRA issue types. Are you able to add the issue type Test to your JIRA workflow? This would alow for you to close, etc, the Test issue type.

Kind Regards,

Emily

Graeme Fidler
Contributor
August 5, 2014

Hi Emily

Thank you for your comment.

I didn't think you were meant to 'Close' a live 'Test' within JIRA?

Regards

Graeme